|
|
March 20, 2000
For more information, contact
County Public Information Officer
David Wert
(909) 387-4082
dwert@cao.co.san-bernardino.ca.us
Dedication set for Grove Basin
flood control project
Rain
won’t threaten San Bernardino County’s dairy industry the way it has in years
past thanks to a $10 million county flood control project to be dedicated this
Friday, March 24.
During
major storms, the Grove Basin and Riverside Storm Drain project will reduce
flooding in the Agricultural Preserve south of Riverside Drive in Ontario between
Euclid and Walker avenues, said Ken Miller, director of the San Bernardino
County Transportation/Flood Control Department.
The
project will go a long way toward preventing a repeat of the extensive damage
and loss of dairy animals farmers suffered during severe flooding in February
1998. More than 10,000 cows and calves were killed and total damage in the
county topped $20 million -- more than twice the cost of the flood control
project.
“The
floods of 1998 were devastating to San Bernardino County’s dairies, which
contribute $1 billion a year to the local economy,” said 4th
District San Bernardino County Supervisor Fred Aguiar. “I’m proud that we were
able to complete this project efficiently and quickly enough to prevent future
disasters.”
-MORE-
Grove Basin Dedication
Page 2
The
dedication ceremony will be held on Friday, March 24, at 10 a.m. at the
northeast corner of the basin on Grove Avenue just south of Riverside Drive.
Parking is available at the corner of Grove and Riverside.
Supervisor
Aguiar, San Bernardino County Transportation/Flood Control Director Ken Miller,
Milk Producers Council Executive Director Bob Feenstra and David W. Smith,
deputy state conservationist for the Natural Resources Conservation Service are
scheduled to speak at the dedication.
The
Natural Resources Conservation Service, a branch of the U.S. Department of Agriculture,
provided $5.5 million of the funding needed to complete the project.
NRCS is funding the flood protection basin through the
Emergency Watershed Protection program, which has been widely used throughout California
and the nation to protect communities following natural disasters. Projects are
evaluated from an economic, engineering and environmental standpoint and are
completed in cooperation with a local partner, in this case, the County of San
Bernardino.
The
heart of the project is a massive, 25-foot-deep basin just south of Riverside
Drive between Grove and Cucamonga avenues capable of holding more than 105
million gallons of water – equivalent to the amount used in a year by almost
650 typical families. It also consists of storm drains along Riverside Drive
leading to the basin and a drainage pipe south of the basin.
At
the peak of a 100-year storm, the west storm drain will divert 1,230 cubic feet
of water per second into the basin while the east storm drain will divert 720
cubic feet per second. Once captured in the basin, the water will be released
through the drainage pipe on Grove Avenue at a mere 285 cubic feet per second.
-MORE-
Grove Basin
Dedication
Page 3
Whenever
possible, water in the basin will be retained to seep into ground water basins
to conserve moisture for dry years and improve water quality in the region.
The
project will protect dairies in a swath of land stretching from Riverside Drive
south to Pine Avenue between Euclid and Walker avenues.
The
county saved $750,000 to $1 million on the project by having contractors dig
the basin for free in exchange for the 250,000 cubic yards of dirt they hauled
away for their own projects. The haulers were charged inspections fees, and much
of the soil was taken to nearby dairies to construct levees and berms to
control dairy runoff.
The
excavation began in January 1999. In March 1999, construction began on the
basin and storm drains. Utah Pacific Construction built the basin and installed
most of the storm drain for $4.73 million.
The
county had to resolve right-of-way issues before the final western-most stretch
of storm drain could be installed along Riverside Drive between Campus and Bon
View avenues. That was handled in a separate $885,995 contract awarded to Ken
Thompson Inc.
The
total cost of the project was approximately $10 million, including design,
right-of-way acquisition and construction.
The
project was achieved through the cooperative efforts of the San Bernardino
County Flood Control District, the Natural Resources Conservation Service, the
Santa Ana River Watershed Group, the City of Ontario, Utah Pacific
Construction, the Milk Producers Council, the Chino Basin Water Conservation
District and the Orange County Sanitation District.
-30-