| Road | Limits | Area | Yd. | Sup. Dist. | Dept. Contact | Closure Dates | Hours | Contractor | Type of work | Detour |
Conifer Drive, Lark Road, and Oriole Road |
South of Mountain View Avenue |
Wright-wood area |
11 |
1 |
Sharon Lofgran DPW-Permits 909/387-8046 |
10/14/2008 |
24 hrs |
Hill Crane Services, Inc |
Replacing SCE power poles using a crane in roadway |
Mountain Ave, Division Street and Shamrock Drive |
| Goffs Road @ BNSF Railroad Crossing | Between I-40 and Mountain Springs Road | Essex | 15 | 1 | Sharon Lofgran DPW-Permits 909/387-8046 | 10/12/08-10/14/08 | 24 hrs | Bridgewater Equipment Inc. | Replacing tracks and concrete crossing plank | No detour available |
| Middle Control Road | North of State HWY 38 in the Barton Flats Area | Barton Flats | 05 | 3 | Sharon Lofgran DPW-Permits 909/387-8046 | 10/13/08- 10/31/08 | 24 hrs | Joe’s Logging | Cutting down approximately 500 diseased trees | Glass Road |
Wagon Wheel Drive |
Silver Spruce Dr. & Wagon Wheel Dr @ Deep Creek Drive |
Running Springs |
08 |
3 |
Sharon Lofgran DPW-Permits 909/387-8046 |
09/15/08- 10/17/2008 | 10 hrs | Trinity Construction Co. |
Installing a water main line. |
Deep Creek Drive and Silver Spruce Drive. |
Yermo Road |
Alvord Mt. to Field Road |
Yermo |
12 |
1 |
Stephanie Hernandez |
6/13/07 - until further notice |
24 hrs |
County of San Bernardino - DPW |
Investigating structural integrity of bridge. |
I-15 |